Home / Success Stories / Improvement of Roads in Eastern Suburbs – Road No.14 Shivaji Nagar, Govandi, Mumbai
Mumbai, Maharashtra, India | Municipal Corporation Of Greater Mumbai
Road No. 14 at Shivaji Nagar, Govandi, runs adjacent to the Deonar dumping ground—one of Mumbai’s largest landfill sites. Leachate from the landfill, combined with monsoon water accumulation and a rising groundwater table, has rendered the surrounding soil soft and marshy. These conditions severely weakened the pavement subgrade, leading to frequent distress and the need for regular maintenance.
Recognizing the potential of advanced geosynthetic technologies, MCGM opted for a pavement design incorporating systematic subgrade stabilization using geosynthetics.
Conventional soil stabilization using chemical or cementitious additives was considered but rejected due to:
After evaluating cost and lifecycle benefits, MCGM chose geosynthetics as a more economical and reliable long-term solution.
The project consultant recommended a dual-geosynthetic approach at the Granular Sub-Base (GSB) level:
The pavement structure was designed as per IRC 37:2012, using site-specific CBR values and traffic data. The geogrid enhances load distribution and reduces subgrade strain, while the woven geotextile prevents intermixing of soil and aggregate, preserving layer integrity and drainage.
This approach offered:
Executed in 2019, the project met all performance expectations:
It is a road improvement project in Govandi, Mumbai, executed for the Municipal Corporation of Greater Mumbai (MCGM). The road lies adjacent to the Deonar dumping ground, one of Mumbai’s largest landfill sites, and was experiencing repeated failures due to weak, waterlogged subgrade conditions.
Key factors included:
These conditions drastically reduced the subgrade’s load-bearing capacity, leading to recurrent pavement distress and high maintenance needs.
MCGM evaluated options and selected geosynthetics because they offered:
A dual-geosynthetic system was installed at the Granular Sub-Base (GSB) level:
The pavement was designed as per IRC 37:2012 using site-specific CBR and traffic data.
Together, they create a reinforced, well-separated pavement system over very weak ground.
The pavement structure was designed in accordance with IRC 37:2012 (“Guidelines for the Design of Flexible Pavements”), incorporating geosynthetic reinforcement to enhance structural capacity over the weak subgrade.